Avocor 138 Screen PRODUCT INSTALLATION
INSTALLATION ENVIRONMENT
1. For wall mounting, the wall should be a load-bearing structure. Installation on special wall structures such as glass, marble, porcelain, or hollow walls may result in additional costs as these structures cannot bear the weight of the product and may need special installation processes.
2. The installation is limited to punching the load-bearing wall, hanging, or mounting on a vertical bracket; any special installation, such as wall reinforcing or steel structure installation, will be subject to additional cost calculated as actually incurred.
3. We assume no responsibility for any potentially hazardous installation designated by you despite the advice of our installer, nor shall we be held liable for any damage to any other item caused by your use of any non-our company standard/proprietary hanging bracket. STRUCTURE INSTALLATION.

STEP 1: ASSEMBLE THE BRACKET 1. Find the parts according to the parts breakdown of the bracket assembly, as illustrated below:

2. Tighten the installation screws with the corresponding tools. The assembled bracket is as shown below:

STEP 2: INSTALL THE HANGING BARS 1. Select the corresponding accessories to install the hanging bars, as illustrated below:

3. The hanging bars and the bracket are assembled, as illustrated below:

STEP 3: ASSEMBLE THE PANELS
1. The integrated display is delivered with the panels joined into a column according to their numbers. A total of five columns are joined.
2. Connect the panels with a tool using hook locks on the top and bottom in the position marked in blue and spring side locks on the sides in the position marked in red, as illustrated below:

3. Install the hanging plates on the corresponding panel with two M8*25 hex head bolts and flat spring washers.
4. Remove the locating pins on the top panels and the spring locating pins on the leftmost column viewed from the front. Then secure the upper edging with a cross screwdriver, as illustrated below:

STEP 4: ASSEMBLE THE ENTIRE MACHINE * Make sure that the bracket castors are tightly locked and the hanging bars are level;
1. Hang the panel from center to sides. Place the hanging hook of the panel on the hanging bars of the bracket.
2. Install the adjacent second column so that the hanging hooks are on the hanging bars and the adjacent side planes are closely attached together. Pull out the side spring locating pin and insert the entire pin into the corresponding locating hole. Then rotate the side hook lock with the corresponding hex wrench until the panels in the left and right columns are fully locked, as illustrated below:

3. Install the panels in the rest of the columns, as illustrated below:

STEP 5: ASSEMBLE THE LOWER SIDE FRAME * The lower side frame assembly is made up of lower frames 1 and 2, connected by a connecting plate.
1. The lower side frame assembly is secured on the lowermost row of panels with rotary hook locks, as illustrated below:

2. Wiring: Red indicates a five-branch power cable, and purple indicates a signal cable (network cable). Connect the power and signal cables between the panels according to the diagram.
3. Then, connect the signal and power cables to the lower side frame assembly. Insert each column of the signal cables into the corresponding columns of sockets according to their respective positions only. Plug in the power cables with 3p plugin connectors according to their respective positions, as illustrated below.

STEP 6: INSTALL THE MODULES * Install the modules from left to right, from right to left, from bottom to top, or from top to bottom as appropriate for the installation environment on the site. * Repair any improper flatness during assembly.
1. The modules shall be hard-connected to the hub board and the connectors on the modules. Use the right strength and avoid forceful insertion during installation, as illustrated below:

2. Serial numbers of panels and modules. Each of the panels is delivered with a number marked on the upper right (on the inside), which represents the installation position of the panel at the time of factory correction. Each of the modules is also marked with a number (on the back). For example, in the number 16-5, 16 means the lamp board is installed in panel 16 at the time of factory correction; 5 means the position inside panel 15.

3. To achieve a better display effect, you can install the modules according to their serial numbers at the time of factory correction, as indicated in the diagram.

STEP 7: INSTALL THE LEFT, RIGHT, AND UPPER EDGINGS & THE LOWER SIDE FRAME COVERS
1. The left and right edgings are clipped in the side spring locating pinhole with clips (as previously described, the spring locating pin on the left most of the screen should be removed, and an edging should be installed), as illustrated below:

2. Antenna board assembly: a. Remove the four M3*5 screws that lock the cloth and cover, separate the cloth and cov er, and install the WIFI module.

b. During the wifi module installation, align the holes at both ends with the screw posts. After the wifi module is installed, use M3 hexagon nuts to secure it.

c. Use M3*5 screws to lock the wrap and cover.

3. Power cable installation: a. After threading the input power cord through the hole at the back, connect the brown wire to the 'L' (live) terminal, the blue wire to the 'N' (neutral) terminal, and attach the yellow ground wire appropriately. The red frame indicates the entry point for the power line, while the blue frame designates the output for the three-in-one board power cable. The power cable should exit the control box through the hole marked by the yellow box.

4. Install the lower side frame covers from left to right according to their respective positions indicated on the installation diagram and secure them with a cross screwdriver and M3*8 black countersunk head screws. The installed covers are as shown below: